The afternoon of July 1, Putian City, Fujian Province People's Government and theFujian Electric Power Co., Ltd. signed a "five-second" network development strategic cooperation agreement. From the signing ceremony, noted that National Grid Fujian Electric Power Company "five-second" period will invest 4.665 billion yuan for power grid construction and transformation of Putian.
According Putian "five-second" network planning, to 2015, Putian network planning new(expanded) 500 kV substation was built two, capacity 1.75 million KVA; new(expanded) to build six 220 kV substations, capacity 90 thousands VA; new (expanded)to build 110 kV substation 19, capacity 924 500 kVA; new 500 kilovolt transmission line352 km, 220 kV transmission line 111 km, 110 kV transmission line 260 km. At the same time increase to build a comprehensive battery replacement station 1, station abattery distribution services, exchange of charge pile 270. Launched a new round ofupgrading rural power grids work, the city's 2012 dual power supply for all towns to buildthree rural electrification, electrification of 64 villages; Meizhou Island in 2011 after thecompletion of the second loop into the island to meet the island's electricity load growthneeds and improve supply reliability.